This lesson explains about how stages can be locked or unlocked in the Budget vs Actual area of CMAP. Once a stage has been locked, users will no longer be able to allocate time to it as the stage will appear grey and not selectable in their timesheet.
Step 1: Go into the Projects tab, find your project and click into it.
Step 2: Click on the Budget vs Actual page.
Step 3: Click on the percentage under the Progress column (marked in blue).
A box will appear showing the progress of your stages to date.
On the left hand side of the box, you will notice a padlock symbol.
Step 4: Click on the unlocked padlock to lock the stage. The padlock will close.
The stage will then be locked to the users so they cannot book time to it within their timesheet.